Dear Experts,

we are having only single cycle time based & performance based preventive maintenance plans. The individual plans are weekly, monthly or based on specific counter readings. Now i want to schedule it automatically through IP30. since there are plans with different units like days or hours how can i schedule it through IP30? is it possible to run separate IP30 for counter based single cycle plans? Is it ok if I run the program on every midnight? I am confused on the scheduling through IP30. please give me the clarity...Please do the needful.

Thanks & best regards,

Praveen

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Sep 17, 2008 at 09:13 AM

    Praveen,

    Yes you can run IP30 with single cycle plans.

    As IP30 can run for many hours (dependent upon number of plans) it is best to schedule the IP30 job at a time when there are fewest users on-line e.g. midnight on Saturday or Sunday. The timing is very much dependent upon your organisation.

    [Here|http://www.sapfans.com/forums/viewtopic.php?f=7&t=316910] is some good background info.

    It should be someones responsibility in your organisation to review the scheduling log after every IP30 run

    PeteA

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 17, 2008 at 09:53 AM

    use the sort field to run different groupings of plans - this way the scheduling runs can be broken up into meaningful lots

    set up variants and do as Pete suggests

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      As it said in above mail group ur maintenance plans with reference to sort field and make use of it.like put all singlecycle plans with day as unit sort field as day single cycle.

      Regards,

      N.Nagaraju

  • author's profile photo Former Member
    Former Member
    Posted on Sep 17, 2008 at 10:10 AM

    Dear Praveen,

    Please crete variant and make use of T-Code SM37 for executing program automatically after defined interval.

    Regards,

    Kaushal Rai

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.