Dear Experts,

we are having only single cycle time based & performance based preventive maintenance plans. The individual plans are weekly, monthly or based on specific counter readings. Now i want to schedule it automatically through IP30. since there are plans with different units like days or hours how can i schedule it through IP30? is it possible to run separate IP30 for counter based single cycle plans? Is it ok if I run the program on every midnight? I am confused on the scheduling through IP30. please give me the clarity...Please do the needful.

Thanks & best regards,

Praveen