​Incorrect MRP suggestion! MOQ

Apr 06 at 12:09 PM

38

avatar image

Hello, I need help.

For some items registered without a MOQ (MM03 and ME13), MRP suggests buying with a MOQ of 500 pieces, but I did not find anything in the register that shows that it contains MOQ 500 pieces. Would anyone know if there is any field other than MM03 and ME13 that is registered MOQ?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Jürgen L
Apr 06 at 12:15 PM
0

How do you know that the MRP quantity of 500 is a MOQ (minimum order quantity) and not just the quantity that you need to fulfill an order?

What does MD04 and CO09 show? What MRP type and lotsize do you use?

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Thanks for the reply. I found the problem, was registered the "Quotization" in the MEQ1 with a MOQ of 500. Thanks!

0
Caetano Almeida
Apr 09 at 07:31 PM
0

Hello Enio

MRP will determine the replenishment quantity based on the material lot sizing. Check what is your lot sizing procedure defined in the material master and if you have additional settings, such as a minimum lot size or a rounding value.

Regards,
Caetano

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Thanks for the reply. I found the problem, was registered the "Quotization" in the MEQ1 with a MOQ of 500. Thanks!