Hi,
To all Experts,
This is regarding the bom explosion in subcontracting P.O(scenerio).Scenerio prob. is explained as follows -
1) I have an assembly which includes the semifinish & raw materials.
2) By cs11 it explpodes whole BOm
3) When i made P.O. for job work order(subcon.), in mateial data view it displys only the semifinish components(i.e. component or explode bom) ,but not the raw,which we want to send to vendor.
so due to above,how we can determine, what the material we are sending to vendor?
In short i want to explode the bom in po,in which it displys the semifinish as well as its raw.
So please suggest a propper solution for above query.
Hoping suggestion quickly
Thanks in advance
Manish
Hello Manish,
Could you please tell me how you have resolved this problem. I have the similar requirement.
"want to explode the bom in subcontracting po,in which it displys the semifinish as well as its raw."
we are exploring the PHANTOM ASSEMBLY but still no luck.
When i set at BOM item level - Phantom Assembly off indictor and Spec. Procurement 50
system is still requesting for transfer of Phantom Assembly instead of components to the vendor.
Thanks in advance
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear shyam,
I didn't found your new post about the issue. I hope u have solved the problem.
If not please mail me as unable to find your thread.
With best regards,
Manish K. Bachate.
SOLVEED.WITH THE USE OF PHANTOM ASSEMBLY CONCEPT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Std. system never exploed multilevel BOM in any transaction data , It will exploed only till first level only,
bye
aMit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In ME38 Delivary schedule we can explode BOM.After delivary schedule go to item->components inthat we find out BOM explosion
Pl. check spl procurement type 30 is maintained in the mateiral master and subcontracting item category L
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear ,
I think you have to Maintain the BOM in single level,
rg
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.