confirm the Network

Hello experts,

Can any body tell me how to settlement the activty & how to comfirm the network & activity of the project? how to run the result analysis of the wbs billing element.

Regards

Raman T S

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 16, 2008 at 11:41 AM

    Hi,

    You can confirm activities thru Network in CJ20N.

    Open project->select network->activity overview->select activity->edit->activities->confirm.

    This will take you to tcode CN25 or you can directly go there and confirm the activity by providing network no and activity no.

    For settlement, first you have to maintain settlement rule against all those wbs elements (thru CJ20n) you want to settle.

    For result analysis, first maintain RA keys against wbs elements. Then run RA for projects thru KKA2.

    Now for settlement go to tcode CJ88..provide data and execute.

    Regards

    Abhinay Gautam

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 16, 2008 at 12:04 PM

    Dear,

    There is another very easy method of confirmation bu CN41 the envoirnament and select confirmation .

    Here you can select Individual or Collective confirmation or you can select the paticular ativity and the go to enviirnment tab and select the confirmation.

    Put actual value and save it.Activity will confirm.

    Then CJ8G and create the varient and create collective sattelment of actual value.

    Regards.