ChaRM: schedule automatic import to QAS system via background job?

Hello,

is it possible to schedule a background job every 10 min for the import to QAS to speed up the process instead of doing this every time in the schedule manager?

Nevertheless there is only an option to schedule daily, but I want it every 10 min!

I tried report /tmwflow/scma_trorder_import but it is not working, it wants an variant, but it is not possible to create one!

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Sep 18, 2008 at 10:03 AM

    Hi John,

    why it should be not possible to plan a job via SM36?!

    As step you can use an ABAP programm with report "/tmwflow/scma_trorder_import"

    Please let me know whether or not it works, because I have the same problem.

    Thank's!

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 10, 2009 at 11:27 AM

    Hi John

    Did you ever solve this issue? I have the same problem, i would need my job to run every 15 min, even if the tasklist have a variant its not picking this up when the job is running.

    Please guide me if you know the way!

    Regards,

    Daniel

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 23, 2011 at 02:16 PM

    I am having the same issue. Should be able to schedule import from the Charm task plan on an hourly or xx minutes interval. But Daily is the only option. You cannot schedule in SM36 because it wants a variant and I cannot create one there. Any solutions would be appreciated.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      we have solved this as part of our ChaRM enhancement package, but it is unfortunately not for free.

      If you are still interested, my contact details are available in my business card.

      Regards,

      Christoph

  • avatar image
    Former Member
    Jun 14, 2013 at 01:31 PM

    Hello,

    It's an old post. but to give a new answer :

    - On your QAS system in your import queue set a fliter by Project ID.

    - Import all with schedule.

    That's it.

    Add comment
    10|10000 characters needed characters exceeded

    • This is then bypassing any ChaRM transport methodologies - technically and transport perspective is the same, but tracking and reporting updates might suffer and you need to open project status switches.

      Solution is to create an own report to call the task on the task list via FM /TMWFLOW/TASK_START.

      This report can be scheduled as any other report, executes imports via schedule manager and provides logging. No need to open status switches and thus jeopardizing security and traceability in ChaRM.

      Regards,

      Hannes

  • avatar image
    Former Member
    Dec 23, 2014 at 09:16 AM

    Hi John,

    Please see Note 1897163.

    Use Option 1.

    When specifying Period Values, select Other Period and enter 10 in the Minutes block.

    This will Auto import.

    Regards,

    Calvin van der Walt

    Add comment