Hi Experts,

I have a contract release order with 5 line items. For the 5th line item the STAPO field in EKPO is activated. Below are the details of the line item.

1. Delivery Completion indicator not activated in PO line item.

2. PO line item not deleted/blocked.

3.Final Invoice field not activated for PO line item.

Only change done on the line item is that the confirmation has been modified to Inbound delivery.

Due to the activation of the STAPO field, queue from EWM system is blocked and not able to post GR.

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor
0 Kudos

The EKPO-STAPO field interacts with the deletion of a PO item.

What you describe then looks like an inconsistency. It would certainly help if we could see the change history of your PO item 5 .

There is an old OSS note with a Z-program to fix such inconsistency: 358293 - ME21N: Problems when deleting/undeleting

You may try if it finds your PO item as inconsistent and if then can fix the situation.