MRP Run for with selection of component and selective peroids

Apr 05 at 02:05 PM

43

avatar image

Dear Experts

My business scenarios is manufacturing of consumable product (Tooth brush),Here two type of material is used for raw materials

1.ZROH -Raw material

2 ZPDK -Packing material

Raw materials are imported from other countries,lead time is 120 days

Packing material are getting from near ie lead time will be of 1 day only

MRP result:

For raw materiel proposal has to come from 6 months for which I'll entered in Demand but for packing material proposal has come from 1 month same demand.

My packing material planning will be of firmed planning (ie current month).

But Raw material planning will be of average (6 month)

I will enter the PIR for 6 month,I will run the MRP two time

First time (planning horizon-6 month) proposal will be of ZROH (raw material)

Second time(planning horizon-1 month) proposal should be ZPDK material

Note:

With out changing planned independent requirement (MD61)

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Caetano Almeida
Apr 05 at 07:09 PM
0

Hi Prasath

I think that you should keep the PIR forecast for the packaging material as inactive in the future. You can use transaction MD70 to copy to inactive forecast to the active version once a month for the packaging material.

Another alternative, would be to make the future forecast not relevant for MRP using BAdI MD_CHANGE_MRP_DATA.

Regards,
Caetano

Share
10 |10000 characters needed characters left characters exceeded
Prasath Elumalai Apr 08 at 11:22 AM
0

Thanks Ceatano

PIR will not be of specific to Packing material or raw material,PIR for Finished product only,Could you please explain me how to make inactive for packing material,

Is any possible to maintain the planning horizon MRP group wise,In my case I maintaining separate MRP group raw and packing material.