Disable acivity input when confirming CO11n

Former Member
0 Kudos

Dear SAPper,

How can we disable the input box when doing CO11N.

for example:

we have 4 activities : setup, processs, labor, and overhead

when user confirming order he/she should only input setup process labor, the overhead value

should not be changed ( all activities value default from routing but only overhead can;t be changed)

Kindly help and thanx.

Best regards,

Freddy Ha

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Go to TCODE :OPK0

This is the single screen entry for confirmation.

Select the profile you are using & in the tab Defaults Activity -tick mark Close or

go to section default values & select "Activity"- Hidden and fix tick mark

Please try with this and come back.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

I try OPK0,

Yeah it can hide the activies.

Something bother me, if the activity line is vary. how can we deal with it.

When i test the OPK0 yeah it suits the requirement.

do you have any idea to if the activity line is vary?

For example.

Order 1 activity = setup machine labor overhead

Order 2 activity = machine overhead

Any idea is very appreaciated and helps.

Best regards,

Freddy Ha

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

If you want to use same activity type in the routing then,

go to CR02--costing tabe active tick mark as reference indicator in front of activity type.

So all these activity type remains unchange in routing and confirmation also.

Hope clears to you.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

I mean the value of the activity, still same with my first issue.

You told me that i can use OPK0 (thanx very much).

But if i have several order with dffrent activity number.

For example

order 1 : machine overhead

order 2 : setup process labor overhead

According to order 1 i will set in OPK0 the second paramter is hidden.

This condition is valid for order 1

but if the user try to confrim order 2 then the second actitivy(process) it will be hidden too.

Do you have any idea abiut this.

Thanx.

Best regards,

Freddy Ha

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

It is not possible for prticular order you can change it.

Best way you should hide all the activity along with ref indictor in WC.

By this you can post the activity according to the routing without change.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

Yes, i think you are right.

Thank you very much for helping me.

Good Day Mr. Brahmankar.

Best regards,

Freddy Ha