I want to generate automatic maintenance order through preventive maintenance plan.
Structure of my plan
Daily
weakly
monthly
3monthly
Call horizon -80% for 10 year
Star cycle Date 31/03/2018
after completing plan i tried to schedule in IP30, but it generates order today date 4/04/2018 .
My issue is that Maint. plan should generate order at 01/04/2018,02,03/04/2018
Please Discuss in detail about IP10, IP30 at what time should we use?
Thank You.