factory calendar

hi, everyone.

What's the usage&influences of the factory calendar in the project profile?

Is that relating to scheduling? If so,how?

In our project the factory calendar is W8(every day is working day), but when i schedule on the network,i don't see any influence(weekends are automatically subtracted).

regards,

tiger wu

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Sep 14, 2008 at 01:44 PM

    check the factory calendar for the work centre used on the networks, this could be different from W8 - the scheduling is based on the factory calendar of the work centre

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 15, 2008 at 03:53 AM

    Hi Tiger

    In project profile, it uniquely identifies the factory calendar valid for the plant. It is defined on the basis of a public holiday calender.

    Scheduling uses the factory calendar in the work center if you have entered a calendar in the work center. Scheduling uses the factory calendar in the activity or relationship if you have not entered a calendar in the work center

    Scheduling uses the factory calendar for the plant only if you have not entered a calendar in the work center or activity.

    Regards,