CM07 overload for 2 month for one workcenter.

Hi All,

for one workcenter there seems overload in cm07 when checking with planning scenario while wihout planning scenario load looks normal.Also in cm01 load looks normal.we are having standard SOP ,but looks like from sales data file that much demand not uploaded...what may be the reason

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Nov 01, 2016 at 01:49 PM

    Hello

    When you are not using the planning scenario, system only reads real planned and production orders. When the scenario is used, system reads only LTP simulative planned orders and this is where you have an overload. So you must check the planned orders under your scenario and ensure that there is no overload.


    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 02, 2016 at 02:37 PM

    You need to check why these planned orders were created. Possibly, you have a huge demand for those materials.

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 02, 2016 at 03:06 PM

    There are only few who got so high demand other simulative are ok....workcenter also looks ok...

    Add comment