Folks,

I have the following requirement:

I have 1 plant with 2 SLOC's:

SLOC1 = warehouse - assigned to WHS WH1

SLOC2 = service van

SLOC1 delivers to SLOC2; i.e. the van has stock requirements at SLOC1.

How can I process these requirements from SLOC1 to SLOC2? The required materials need to be picked in WM from SLOC1. The van will be at the dock of SLOC1 to pick up the materials. I dont want to process this via shipping.

Any suggestions?

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Sep 12, 2008 at 10:13 AM

    hi

    is ur stores r with in plant or far apart

    u can use movement type 311 or combination of 313 nad 315

    regards

    kunal

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      The van picks up the material at the WHS itself. The 311/313/315 is an option, however, the requirements should be processed via SAP as well. So the service van has stock of a certain material and becomes below safety stock and for example MRP creates a reservation which will then be procssed via WM.

      Other scenario is that a service order is put in place with certain components. These components are combined in a reservation as well.

      Can MRP create reservations and how can I process these reservations in WM?

      Regards,