Former Member
0 Kudos

Hi Guru,

i am changing the price by using the MR21 transaction code.

but while changing the price system it give the following error.

A current or future standard price exists for material xxxxxxx.

please give me the valid information on this. it is very urget i have to change this today.

Thanks

By

siva

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

this had been solved.

Former Member
0 Kudos

Dear,

If your problem is solved please explain your solution because your question is show 126 person and give answer 13 person.

So all know problem solution and if your problem is solved with the answer of SDN user then give points to him

Regards,

Mahesh Wagh

Former Member
0 Kudos

Dear,

Same problem face me at the time of price change.

main reason is costing is already run for this material.

Due to costing material price is already maintain for this material.

So if you want to change price of this material contact your costing person and reverse costing for material. Then try to change material price.

You can check it with MM03 - enter your material code, select accounting 1 view, Here you can see Std Cost Estimate button.

Click on it, You can see three button,

Future,

Current,

Previous.

Click on Current and future and see costing for material.

If costing is run for material in current period then try for future date.

Best way is reverse costing and then try to change price.

Regards,

Mahesh Wagh

Former Member
0 Kudos

remove future price in mm03 accounting data 1 and then enter new price in mr21.

regards

points if solved/helpful

former_member192897
Active Contributor
0 Kudos

Go to Material Master Accounting View 1 and Check whether any Future Price is Maintained in Future Price Field.

Regards,

Ashok

Former Member
0 Kudos

in the accouting view 1 future price not maintain.

thanks

siva

Former Member
0 Kudos

hi

the message itself telling u that u maintain standard price for the material .

thanks reagrds,

srinivas kona

former_member192897
Active Contributor
0 Kudos

Could you Please tell me the Price Control of a Material whether V or S

Regards,

Ashok

Former Member
0 Kudos

hi,

i have maintain the Price control : S.

Thanks

kannan

Former Member
0 Kudos

Hi,

i got the following help from the sap.

please guid me how to solve this error.

A current or future standard price exists for material

Message no. CKPRCH025

Diagnosis

A current or future cost estimate exists.

Procedure

You can set the price of a marked cost estimate through the radio button 'Default Planned Prices' and release it by saving.

Thanks

siva

Former Member
0 Kudos

Dear,

Reverse your costing for material with your costing person who run costing for material then try to change.

You definitely done it.

Regards,

Mahesh Wagh

former_member192897
Active Contributor
0 Kudos

I have found one Link Related to your Issue. Please go thru it. It would solve your Problem.

http://sap.ittoolbox.com/groups/technical-functional/sap-acct/standard-price-change-mr21-848544

Regards,

Ashok

Former Member
0 Kudos

Hi,

costing run date for current is 06.02.2008 and previous perion is 04.01.2008.

please giv eme the valid input on this how to change this.

Thanks

siva

Former Member
0 Kudos

Dear,

First check Future, if it is existing so you first reverse it other wise check with 07.02.08 in MR21 also try with MM02.

Regards,

Mahesh Wagh