Skip to Content
avatar image
Former Member

Certain buttons greyed out in CC 5.2

Hi Guys,

We are working on CC 5.2

Some buttons in the background jobs window is greyed out. for eg log button, Unable/disable button, terminate job button... Can anybody suggest what is missing

Parveen

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 15, 2008 at 08:29 AM

    Hi again Parveen,

    I guess you are runnning SAP GRC CC 5.2 (SP09) where that issue was raised. The schedulng for jobs is not working properly. Eventhough you delay the execution for a job, it starts inmediatly.

    According to SAP GRC Support, such issue has been fixed with SP10. We have not had the time to test it but I guess it will be fixed.

    Hope it helps. Best regards,

    Imanol

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Guys,

      there was some action (Authorisation) relating to CC missing in Net weaver role.. Just search and assign it to the role ..... it will fix the problem...

      Parveen

  • avatar image
    Former Member
    Sep 12, 2008 at 01:08 PM

    Hi Parveen,

    That is the proper state for the already executed jobs.

    Such buttons are enabled just when the job is scheduled or running.

    Try to schedule any process in background for a future date and check the buttons state.

    Hope it helps. Best regards,

    Imanol

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi

      When i schedule a background job even after selecting a delayed start option, its status in the background job window show running.. and the buttons still greyed out..

      Parveen

  • Sep 12, 2008 at 08:23 AM

    Can you please add some more information?

    - Background daemon is running (Note 999785)?

    - is it still grey if you klick on one of the job lines?

    Frank.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 16, 2008 at 08:11 AM

    I am glad to see you solved it.

    Best regards,

    Imanol

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 22, 2008 at 07:53 AM

    Hello everyone,

    All buttons are active in AC 5.2 SP 9 as well.

    The only difference is that the delayed job is executed immediately and also gets scheduled for later execution.

    I give you a simple scenario in SP 9.

    1) go to background jobs > Schedule Analysis

    2) give a job name

    3) select delayed start

    4) keep today's date for "scheduled selection"

    5) enter time "current time + 1 hour"

    6) under period selection > select schedule periodically

    7) select daily > values = 1 day

    8) enter end date = tomorrow's date.

    you can now schedule this background job, and you will see the status of this background job as running and then after first execution it will be "ready"

    during running mode you will be able to terminate this job, but when it is in ready mode you can enable and disable this job absolutely fine in SP9.

    I hope i made my point clear.

    Best Regards,

    Amol Bharti

    Add comment