on 04-04-2018 7:51 AM
Dear All
We have migrated ML in existing landscape in ECC6.0.Before ml activation,we have closed all production orders (teco status) and close all open purchase order(mr11).
In the ckmlcp determine sequence is not selecting any materials and due to this multi level price difference not generated.Checked in table ckmlhd-price determination is "2" with "S" against all sale order cost estimate number line items,whereas material master is showing price determination 3S.
The table ckmlpp-consumption qty field is showing with zero value against period status 1,31 & 40.
We are trying to change the price determination from 2 to 3 via ckmm but unable to change.
Kindly advice how to handle this issue.
Thanks
Warm Regards