Dear Gurus,

Can we take a report on % completion of activities?

Suppose network have 10 activities under different WBS, then can the report be run showing % completion status of all activities.

And can the similar report be obtained for texts mentioned in the activities?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear,

You should use the T code CNE5 and select the N/W or WBSE OR Project then run the report and select the % work ,remaining work .

Try this .

Regards.

Answers (1)

Answers (1)

Former Member
0 Kudos

U can go thru CN47N prior to which u need to put confirmation % for the activities