GR has been restrict before confirmation. So, we need the qty in CO11n to refer to the GR qty, is there any standard ways to do this?
closed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can maintain the auto GR tick in T.code OPKP (Production scheduling Profile). and also use with tollerance limit in workscheduling view.
Please check my reply in this link,
[Thread|https://forums.sdn.sap.com/click.jspa?searchID=16167113&messageID=5916777]
Regards,
R.Brahmankar
Edited by: R Brahmankar on Sep 11, 2008 3:02 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use auto Gr so u can make gr at a time of production order confirmation & GR quantity be same as yield quantity.
for it plz take operation controle key having Auto Gr in standard it is PP04.
Thanks
Rakesh Sxena
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
To set confirmed qty as GR qty and also GR from CO11N.You have to use either
- Contorl key (PP03) with auto GR functionality at the last operation of Routing.
or
- Set auto GR tick in T.code OPKP (Production scheduling Profile)
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.