Is it possible to change the timestamp of basic dates in production order (co01)?

Apr 04 at 02:50 PM

37

avatar image

Dear experts,

1. I want to change the basic date/time by default its taking 00:00. Can we change the time as per our requirement. And for some orders its showing 24:00 as end time how its calculating.

2. And is possible to copy the scheduled time to basic timestamp ?image007.jpg

image007.jpg (82.5 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
RAJASEKAHARA REDDY BANNURU Apr 04 at 03:33 PM
0

Hi Suresh,

These Date & time Stamps are the results of the Scheduling type used in the Production Order.
Could you please try to Create the Production Order with Current date Scheduling
Then, your Basic date & time will matches with that of the Scheduled date & Time
Please find the attached screen shot for your quick Ref
Kindly check & let me know, your feedback/comments : Thanks & Regards : Raja



bxczl.png (83.4 kB)
Show 3 Share
10 |10000 characters needed characters left characters exceeded

Hi RAJASEKAHARA REDDY BANNURU

Yeah its getting changed but as u said its not getting changed on current date if we keep the scheduling type in backwards or forward in time its changing.

So we no need to do cm22 for changing this. because i found one more solution by changing of capacity we can change this is like that?

0

Hi Suresh
Thanks for the quick feedback.
The default scheduling type, to be followed for the Production Order is dependent on the Scheduling Parameters maintained, for that Order Type. Please take a look of the your Configuration settings . T code : OPU3

Thanks & Regards: Raja