Is it possible to change the timestamp of basic dates in production order (co01)?

Dear experts,

1. I want to change the basic date/time by default its taking 00:00. Can we change the time as per our requirement. And for some orders its showing 24:00 as end time how its calculating.

2. And is possible to copy the scheduled time to basic timestamp ?image007.jpg

image007.jpg (82.5 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Apr 04 at 03:33 PM

    Hi Suresh,

    These Date & time Stamps are the results of the Scheduling type used in the Production Order.
    Could you please try to Create the Production Order with Current date Scheduling
    Then, your Basic date & time will matches with that of the Scheduled date & Time
    Please find the attached screen shot for your quick Ref
    Kindly check & let me know, your feedback/comments : Thanks & Regards : Raja