PP Component Scrap x LTP

Hello All:

I've scheduled a change in the Material Master for a determined component.

I put 5% component scrap to this guy to be activated only in 01.01.2009 in MM12

If I look the material in this date, the change is there.

So I create a LTP scenario and put a requirement in MD62 to this material in 02.2009 (monthly)

I've created a scenario and run MRP for this scenĂ¡rio, but the system did not consider the change.

The scenario was created to long term planning and the flag to switch off scrap calculation is not set.

Does anybody knows why did not LTP consider the component scrap ?

Thanks in advance

Luis Henrique

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 10, 2008 at 09:34 PM

    Any changes that you make to material master records are recorded in change documents. In the case of scheduled changes, the change is stored in the change document and not in the material master record itself. The date at which the change is to take effect is stored in the document header. Such changes have to be activated.

    After the changes done, you need to run MM13 to activate the change.

    pl come back if required

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear,

      You are doing some think worng

      In MM12...you have done the change which will be valid from 01012009.

      Now Run the program-MMCHACTV on daily basis in background...so that on 01012009, system will activate the scheduled change required.

      Now in your case actually you are running the LTP for next year and you need to change to reflect from that date.

      This can be done only through Change number and not through the scheduled change alonge with background.

      Mm13 or prog MMCHACTV is used to reflect the data in real time of change and

      chenage number method is required in you case where you want the change to be refleted from that date that in future, but the data to be refleted from future date so that you can plan.

      I hope you are now clear about the difference bewteen changingb the data with change numb er and scheduled change using MM13.