statistical wbs?

our first level wbs is statistical. When i right-click the first level wbs to create a network, it jump into the settlement rule maintenance view. If i create a network in a non-statistical wbs, the case will be different.

Can anyone explain why and how to configurate it satisfy the fist case? Thanks!

regards,

tiger wu

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 10, 2008 at 02:10 PM

    Hi,

    System behavior is normal. When you create network below non-statistical WBS, system knows that cost which would be posted are to be account assigned to WBS. In case of statistical WBS, as you cant post real cost on it, system is asking where you would like to settle costs in future.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      thanks.

      If i create a new 'activity control key' ---PS06 for the activities assigned to the network.

      In PS06 ,the 'cost' checkbox is not selected.

      then when i assign the network to the statistical wbs, the settlement rule view will not appear.

      Does the configuration make sense?

      regards,