Cost not captured while posting PR/PO/SA/GR. in a Project.

Hi All,

I posted a schedule agreement to a particular G/L account,and found that the cost is not captured in budget report for the project.

This problem also exist for PR/PO/GR.

What could be the reason for this and how could it resolved.

Please help.

Reagrds,

Vishal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Sep 10, 2008 at 02:50 PM

    in budgeting config check the business transactions for tolerance limit config to ++++

    run cjen to update PSJ for your project

    check if budgeted values are shown??

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 12, 2008 at 04:33 AM

    Hi,

    I have checked for the tolerence limits . Its ++ (All Activity Groups).

    Also the budget values are shown...

    Now I want to know, what is this transcation CJEN & PSJ for ?

    What is the purpose of using this transcation?

    Thanks& Regards,

    Vishal

    Add comment