on 09-10-2008 12:58 PM
Hi
I Have a doubt. I have two requests to be sent. The second request has to go only after first is transported to target system. Now If I make TOC and transport both together, will this dependability taken care?
Thanks in advance
Hello Sanjay,
Infact merging is the best approach whenever in doubt. A number of times I have 20-30 transport for which even the developer ain't sure about sequence. I simply create another workbench or customiing transport include objects of the original transports and move them. No need for transport of copies either.
Whenever in doubt about the sequence of transports or dependencies take the merger route coz SAP would take care of the versions itself.
Regards.
Ruchit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjay,
As some of the objects in the second transport will depend on the first transport, better try to do a manual tansport.
If you transport together , it will not lead to any problems. But it is best advised to do one after the other in case of dependencies.
Regards,
Radeesh V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If i was you I'll transport them manually in the right order....
Regards
Juan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.