Skip to Content
avatar image
Former Member

procurement

hi gurus

material will be procured at plant level or storage location level?

Regards,

pavan.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 10, 2008 at 12:04 PM

    Hi,

    Procure with respect to plant and kept in the plant with respect to storage location.

    Regards,

    S.Babusingh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 10, 2008 at 12:07 PM

    Hi

    Logically it should be at plant level

    In STD SAP plant is the valuation area

    Any procured material is a valuated stock and hence should be at plant level only

    Moreover storage location is created inside the plant for storing only

    Regards

    Raja

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 10, 2008 at 12:10 PM

    Thankyou for your reply,

    Regards,

    pavan.

    Add comment
    10|10000 characters needed characters exceeded