We have defined tolerance groups for AVAC check against project budget and it was working pretty well. We have taken PO only for budget AVAC check and removed rest others.

We observed that we are creating PR against WBS and budget is getting negative due to no tolerance check against budget at PR level. Its OK so far.

When we are converting these PR's into PO's system is not giving any budget exceeded error. If I am creating PO without referencing a PR I am getting budget error against WBS.

So, my query is how system allowed creating a PO referring a PR against WBS without Budget error? is it standard system behavior?

How can we control it?