budget was exceeded on internal order

Dear gurus

my client facing a problem in internal order.

At the time of creation of purchase requisition we are getting an error that is "budget was exceeded on internal order number 200336".

But in T.code S_ALR_87013019 the amount is available

please help us we are facing same problems in 6/7 orders also.

waiting for your reply

Regards ,

Dipti

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

5 Answers

  • Best Answer
    Sep 05, 2008 at 07:46 AM

    Hi,

    Could be that you maintain tolerance profiles that issue error even before 100% of usage? If not, try to reconstruct the AVC control via KO31 and see if the problem persists.

    Regards,

    Eli

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      Eli's response is fine. Solution given by Eli will resolve ur issue.

      Longback i had same problem, after execution of KO31, issue got resolved.

      wish you good luck.

      regards,

      A.Prasad

  • avatar image
    Former Member
    Sep 05, 2008 at 08:58 AM

    dear friends

    thanks for your prompt response,but in my all internal orders avl is already active.

    is there any steps to br follow after activation

    Regards ,

    Dipti

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 05, 2008 at 09:12 AM

    dear guru

    could you tell me how can i reconstruct it.

    dipti

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 05, 2008 at 10:32 AM

    hi

    i already run this transaction,but no difference found.

    dipti

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 05, 2008 at 10:43 AM

    This message was moderated.

    Add comment
    10|10000 characters needed characters exceeded