Dear all,
When we create a pur.req for external operation (pm03 control key) in maint order,by default the item category comes as D.
where this setting exists.
Regards
KRISHNAN
KRISHNAN
As standard, the PM03 operation control key has the Service flag set. It is this flag that sets the "D" value in the PR.
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
IN customizing Materials Management>Purchasing>Purchase Requisition>Define Document Types
There select ZSER service than double click on Allowed item categories
Here with new entries you can use default are allowed.
Regards,
akushal Rai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Krish,
Our service PR is assigned to Item category of D- ( service)
above setting is in MM part.
Regards
Charles
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.