I open a pro.order before released ,then I do the availability check get a missing parts list, this list including less parts than the missing parts after pro.order released ,why does it caused?which configuration caused?

Thanks,

Helai

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

Helai,

In transaction OPJK, for the Plant/Order type combination - Material availability check is active for both "Create" and "Release" business function.

Two Possibility I see here,

1. When you did the material availability check at the Creation of the order, the stock situation might have been different, than what it was during release.

2. The checking rule defined for Creation and Release are different or type of component check may be different.

Regards,

Prasobh

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks all,it was solved now

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Where was problem exactly? Please assign relevant points for every useful reply.

Regards,

R.Brahmankar

dhaval_choksi3
Active Contributor
0 Kudos

Problem is solved!!!!

Something is missing.

Former Member
0 Kudos

this is caused by "scope of check" something need to be checked ,so now it is ok

I have given all of you the award

dhaval_choksi3
Active Contributor
0 Kudos

Hi Lai,

You can do Material Availability check at the two stage of Production / Process Orders.

- First is to control (Check Missing Part) at the time of Order Creation.

T.code is OPJK - Select order type and Business Transaction -1 at the time of Order Creation

- Second is to control(Check Missing Part) at the of Order Relase.

T.code is OPJK - Select order type and Business Transaction - 2 at the time of Order release.

So it may possible that you have assign different checking group or checks to the above both stages , that's why you got different result regarding missing parts during above both stages.

Regards,

Dhaval

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Please check the availabilty check options.

In T.code opjk (checking control), check for business transactions 1 (avl check during order creation), 2 (avl check during order release).

In scope of planning check if the required stock is included for avl check.

T.code opjj.