I generated Change request thru ECM tcode CC31 i am able to change the bom the same i am able to see in cocm1 tcode also but this change is not reflecting in my affected Production order.Please guide me how to proceed.

Regards

Prakash B.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jan 30, 2009 at 03:13 AM

    Since you have changed the BOM after the date creation of production order. What happens for at the time of Production order creation BOM and Routings are copied to the productino order.Please go to the Production order and Do the PP master data Read there production order will go to Created mod and then release it .. we will be able to find the changes in the components of BOM in production order

    rewd if useful

    BV

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 30, 2009 at 03:13 AM

    Since you have changed the BOM after the date creation of production order. What happens for at the time of Production order creation BOM and Routings are copied to the productino order.Please go to the Production order and Do the PP master data Read there production order will go to Created mod and then release it .. we will be able to find the changes in the components of BOM in production order