MRP run

I want to use MD01 for a plant MRP run and simultaniouly want to restrict some material from this planning run ,can it possible ?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 04, 2008 at 03:27 PM

    Not sure, how to exclude the specific materials for a plant in MD01

    As a work around process:

    For those specific materials, In MRP 1 view change the MRP type to ND,

    correspondingly those materials will not planned

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 04, 2008 at 03:31 PM

    Hi,

    There are couple of ways to do this..

    If you don't want some material to be excluded from MRP Run, then input the MRP Type as ND (No Planning).

    If you want to have the MRP with reference to MRP Controller, Material Type etc..

    then there is a User exit, with which you can do that..

    M61X0001.

    There is sample coading available for this user exit, you can look into that with the Transaction SMOD.

    Regards,

    Siva