committed quantity in production order for those components without stock

Apr 02 at 05:45 AM

36

avatar image

Hi Team,

while i was checking ATP at component level for one item in production order , system is showing committed quantity for one component though there is no PO or stock for the same item, how is it happening?

untitled.jpg (59.0 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Apr 03 at 07:29 PM
0

Hello

Depending on your ATP settings, system may confirm the quantity using the replenishment lead time. Also, you should check the ATP situation using transaction CO09 to understand why it is confirming the quantity.

Regards,

Caetano

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Hi Caetano,

below given the details of CO09,repl lead time and scope of check for components

co09.jpg (95.6 kB)
repl-lead.jpg (67.9 kB)
0

Hello

In CO09 we can see that the record is confirmed after the replenishment lead time, which is zero. In fact, it does not make sense to have ATP with confirmation after the RLT if it is zero.

If you don't want this system behavior, you should change the flag "check without RLT" On your Availability Check Control customizing (transaction OPJJ).

Regards,
Caetano