Hi Team,

while i was checking ATP at component level for one item in production order , system is showing committed quantity for one component though there is no PO or stock for the same item, how is it happening?

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Depending on your ATP settings, system may confirm the quantity using the replenishment lead time. Also, you should check the ATP situation using transaction CO09 to understand why it is confirming the quantity.

Regards,

Caetano

former_member232086
Participant
0 Kudos

Hi Caetano,

below given the details of CO09,repl lead time and scope of check for components

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

In CO09 we can see that the record is confirmed after the replenishment lead time, which is zero. In fact, it does not make sense to have ATP with confirmation after the RLT if it is zero.

If you don't want this system behavior, you should change the flag "check without RLT" On your Availability Check Control customizing (transaction OPJJ).

Regards,
Caetano

former_member232086
Participant
0 Kudos

many thanks, it worked