Hi,

Thanks for clicking this post.

In the current system we have one Purchase Order, with one vendor who supplies the material and also arranges the freight (incoterms DDU = Delivered Duty Unpaid).

We are planning to move from DDU to Ex-Works, with our logistics partner handling the Delivery logistics for us, thus leveraging on their expertise.

If we now create a PO, while the material vendor will be the same, we need a new vendor (Partner Function?) for the Logistics Vendor. When the two invoice us, we are hoping to MIRO on the same PO and thus book freight on to the material.

Is it possible?

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Sep 04, 2008 at 04:22 PM

    Of course you need an extra vendor master for your logistics partner.

    But you create only one Purchase order, to the vendor who supplies the material.

    In this PO at condition level you enter a planned freight, and there you can specify the logistics partner as the one who will send you the freight invoice.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Jürgen Lins

      Hi Jürgen,

      Thanks for your tip. I was looking for some leads to resolve the issue and you provided me with that.

      The rest I'll try and work it out.

      Thanks again.