cancel
Showing results for 
Search instead for 
Did you mean: 

MB1C

Former Member
0 Kudos

HI

Any one please help me on this issue :

Mat. is a miss. part. MRP controller KUNITZ will be notified.

Message no. M7133

Diagnosis

The material 827 is a missing part in plant 0749.

System Response

The MRP controller KUNITZ responsible will be notified via a mail message.

Regards,

Senthil

Accepted Solutions (1)

Accepted Solutions (1)

former_member192897
Active Contributor
0 Kudos

Go to OMBC and Deactivate the Miss Part Active Option and Summarize Miss Parts Options.

Missing parts check active Indicates that the missing parts check function is active at goods receipt.

Use

If this indicator is set, in the case of a goods receipt, other receipts, or transfer posting, the system will check whether the material received is a missing part. If so, the system issues a warning and simultaneously sends a mail message to the MRP controller. concerned.

Dependencies

To activate the missing parts check function, it is also necessary to assign a checking rule to the transaction.

A mail message will only be sent if both the missing parts check and output determination functions have been set accordingly in the Customizing for Inventory Management.

Summarize missing parts mail messages

Indicates that the missing parts mail messages for a material document are issued in a summarized form.

Use

If this indicator is set, the MRP controller of a plant will receive one mail message per material document, listing all missing part materials

If this indicator is not set, the MRP controller will receive a mail message for each material document item that contains a missing part. The mail contains all documents (for example, reservations, orders) for which the material is required.

Regards,

Ashok

Answers (4)

Answers (4)

Former Member
0 Kudos

this message notifys the mrp controller regardin g the recipt of a material which is required in Production order or some thing like that.

nothing wrong in this message so what is the issue??

former_member335885
Active Contributor
0 Kudos

Hi,

Go to and check this configurations.

SPRO - MM - Inventory Management - Goods Receipt - Set Missing Parts Check

Check if missing parts indicator us set for the plant.

If this indicator is set, in the case of a goods receipt, other receipts, or transfer posting, the system will check whether the material received is a missing part. If so, the system issues a warning and simultaneously sends a mail message to the MRP controller. concerned.

Kindly remove this tick and try

Thanks & Regards,

Kiran

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Check in OMBC, here click on "Miss. parts active", here you would have activated "Miss. parts active" indicator for your Plant. If you remove this, it will not give you any message.

Also check other options there.

Former Member
0 Kudos

Hi

Please extend material plant level and enter MRP Controller in MRP Views

Vivek