Hi All,

I have an issue when doing settlement from WBS to AUC/FXA.

Let say the project has a plant call ABCD, then i put settlement rule AUC or FXA..and doing settlement CJ88...but i could settle to AUC / FXA to different plant call CDEF . We decided not to use automatic AUC from IM, we create AUC and FXA from Asset module.

How to validate that Project plant ABCD only could settle to AUC or FXA which have same plant..