Dividing the overhead costs to production orders !

Former Member
0 Kudos

Hi all,

This is regarding the overhead costs split to different Production orders.

The scenario is for e.g There are 3 production orders

P-1

P-2

P-3

and the first 2 production orders(P-1 and P-2 ) are assigned profit center 1

and the last production order (P-3 )is assigned a profit center 2.

In the costing sheet configuration the profit centers are defined and profit center 1 is assigned 10% and the profit center 2 is assigned 20%

The overheads/ other direct costs should be split into 3 pdn orders in the % assigned to the profit centers.

Is this possible? if so, let me know the methodology.

Thanks and Regards

Karpagam

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

absolutelly possible

if you have defined the % per PC in KZS2 and there are costs on the orders (as the basis for %)

than you have to run KGI2 or CO43 (mass)

cheers

matej