MRP in background

i want to run MRP in background for five plants,

how to do it,

please explain procedure.

thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Sep 04, 2008 at 10:15 AM

    Hi,

    MDBT transaction is used to for background MRP Run

    Click the below link for more details on how to proceed further.

    [http://www.sap-img.com/pp019.htm|http://www.sap-img.com/pp019.htm]

    Hope this helps.

    Regards,

    Sankaran

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 04, 2008 at 10:16 AM

    Hi Kailash,

    Use the transaction MDBT. Create a Variant with your requirements from there.

    Regards,

    Srinivas.D

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 04, 2008 at 10:24 AM

    Hi,

    Refer this thread,

    Background MRP

    Regards,

    R.brahmankar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 04, 2008 at 10:29 AM

    Hi,

    Make scope of planning in which you can give your 5 plants whose MRP you want to run.

    Use MD01 or MDBT for running the MRP.

    Srini

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 04, 2008 at 10:38 AM

    hi

    in OM0E you need to craete scope of planning, then you have to craete the MD01 variant with is data.

    this variant has to get sceduled in MDBT. if you want immediately, or periodically yo can deside here.

    -ashok