Valuation type does not exist when doing MSC2N

Hello,

everytime i try to change the production date of the batch in MSC2N, it always prompt me error "Valuation type does not exist". The valuation type is hard lock/grya out with the number as the batch number? i try to look at at the accounting view of the material master it has valuation class value. where does this error come from and how to fix it?

Thanks

Ryan

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Sep 04, 2008 at 09:11 AM

    Hi,

    You need look into the setting for the Plant in OMWC t-code

    OSS note 941082

    Regards,

    R.Brahmankar