externally procured assembly

hi

can u tell me plz....

in BOM one assembly is externally procured but i have mentioned raw material needed for the same.

when i run MRP i should get PR for only assembly not for raw material needed for it.it is not suggested to block material for procurement.

roc

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • Best Answer
    Sep 04, 2008 at 07:57 AM

    Hi,

    For Raw Materials of Assembly, maintain MRP Type as ND (No Planning) in MRP 1 view of Material Master and for Assembly keep PD. And then run MRP, it will generate requirement for Assembly only not for Raw Materials.

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Sep 04, 2008 at 08:07 AM

    thanx pankaj

    other than changing master record ,is it possible,,,,,,,,,?

    roc

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Sep 05, 2008 at 04:41 AM

    Hi

    Plz....

    ROC

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Sep 05, 2008 at 04:50 AM

    Hi,

    Based on the Material master data system will trigger for Planning.

    Without changing the master data it is not possible. You need to put the ND mrp type in the material master for that Raw materials inorder to stop the requirement for that raw materials.

    If the Assembly it self is procured externally then what is the need of the BOM for that Assembly. As you are not procuring any raw materials related to that Assembly.

    If you really need the BOM then instead of maintaining the Production BOM maintain it as Engineering BOM so that you are aware of the BOM with Assembly and raw materials.

    rgds

    Chidanand