Cost estimate with CK40N

Hello All,

I am doing the cost estimate with CK40N, but got the message as no cost estimate found for price update. Can any one please tell me where could be the probable errors.

Thank you,

Best regards

Nivas

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Sep 04, 2008 at 08:58 AM

    Hi,

    Click the detail button for more details.

    I think you need to check the BOM for the material which you are trying to cost.

    Also check whether the material masters has been defined correclty for all the BOM components.

    Regards

    Balaji

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 04, 2008 at 11:09 AM

    Hi Nivas,

    First try doing cost estimate for a specific material using CK11N and then do price update using CK24N.

    If this is working, then your CK40N will also works.

    In first instance, while executing for a single material, you can analyse the errors easily.

    If this is also not updating, then check your customization.

    Regards,

    Sunil M

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 04, 2008 at 11:51 AM

    Hi,

    you must mark and release the standard cost estimate at CK24

    To mark the standard cost estimate, ensure you are in marking screen (see the tile)

    Select current posting period, year, and company code, plant, material -> excute

    Green exception (Marking allowed) will come for company code and Save.

    Now release the cost.

    Press the Release button in the front screen of ck24

    And give same posting period /year/company code/plant/Material -> then remove the test check box and execute.

    Then u will find the new price will be displayed and updated in material master, now system give will message std cost estimated updated successfully.

    Execute release until u will get above message.

    Check whether the costing variant used when CK11N is same as what is marked in for the company code.

    Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 04, 2008 at 02:09 PM

    Fisrt check your costing variant, and check with the actual error you are getting in the CK40N transaction,try to test one material in CK11N .

    Paartha

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 15, 2008 at 04:56 AM

    No costing and accounting views maintained in material masters.

    Add comment
    10|10000 characters needed characters exceeded