PM: Capacity availability for Maintenance

Hi,

I have an PM Equipment which undergo Time based preventive maintenance on monthly cycle. The same equipment is also used for production operation.

I want to see the capacity load coming from maintenance order in CM01.

I have maintained production work center reference in equipment master. Also system condition (0 - not in operation, 1- in operation) is maintained in task list.

I can't see the maintenance load on production work center.

Best regards,

Abir.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Sep 04, 2008 at 08:35 AM

    hi

    pl check in equipemtn master, in location tab have you defined production work centre? and in organization tab the PM work centre.

    and check your PM work centre and production work centre capacity details tick for relevent to finite scheduling,long term planning,

    check wether youhave defined the formulea in work centre and activity types.

    chek the operation hours are entered or not

    in pm order system condition should be "not in operation".

    pl check all

    -ashok

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      hi

      when you creted the PM order and prodcution order?

      what is teh start date and end date?

      have you creted production order also?

      check in CM21 and CM22 or CM50.

      create a new production and maintenace order and check.

      -ashok

  • Sep 04, 2008 at 07:11 AM

    Hi,

    Please refer this thread,

    capacity profile in order control spro

    Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 16, 2008 at 10:23 AM

    OK

    Add comment
    10|10000 characters needed characters exceeded