Our user created a SO and the purchase requisition. Now their requirement to create PO w.r.t. the pur requisition for a PO doc date for 01.10.2009 i.e., to create a PO for the future date. They are getting an error

"Account XXXXXXXXXX requires an assignment to a CO object".

How can resolve this issue? Can anybody help on this pl

Thanks

anifi

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 04, 2008 at 05:55 AM

    Hi,

    Since the posting is happening in current period, that means a correct cost object is being assigned to the cost element. But please check the validity of the cost object. the time perio the cost object is valid is specified in its master record.

    If its not valid, it will not allow to post

    thanx

    alok

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 04, 2008 at 05:40 AM

    Hi,

    This error means the GL account mapped in the PO requires an assignment to CO Object like it can be a cost center, profit center. IO or a project. Until they assign any of the above, the system wil ln ot be able to process the PO. The reason why the system asks for such assignment is the GL account must have been created as a cost element. If it is created as a cost element, you need to assing the CO object. Check in FS00 give the GL account and check the edit cost element tab or alternatively check through KA03 if the GL account is created as a cost element.

    ho0pe this helps

    regards,

    radhika

    Edited by: kolipara radhika on Sep 4, 2008 7:43 AM

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Radhika,

      Issue has closed, problem is profit center need to assign in TC: OKB9. Anyhow, I assigned points you and all

      Thanks all and keep it up

      Thanks

      anifi

  • avatar image
    Former Member
    Sep 04, 2008 at 07:52 AM

    Hi,

    U r going to post PO for future date .

    For this one U need to set commitment configureation and set it for 2009 year.

    After that data will pass now U will get error like gl not assigne to co object.

    U need to assigne element use tcode FS00 and KA01 set cost element.

    Regards,

    Pari