Best Way to assign investment management and put settlement rule in WBS

Hi,

Is there best standard method to put settlement rule and assign investment management which have a lot of WBS structure...rather than assign one by one?

Cheers,

Nies

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 04, 2008 at 04:06 AM

    Hi Nies,

    You can maintain investment profile and settlement profile in project profile using the T-Code OPSA in controlling tab page. This will be defaulted to all the WBS elements.

    Hope this will be useful to you.

    Regards,

    Edited by: Balakrishnan Munuswamy on Sep 4, 2008 6:08 AM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 05, 2008 at 09:35 AM

    Dear,

    There is procedure for the collective generation of setelment rule .

    CJB2 - Individual Processing

    CJB1 - Collective Processing

    In CJB1 you have to create varrient and then you can generate the sattelment rule for meany WBSE .