Is it mandatory to IMPORT a transport into TEST,after RELEASING it fromDEV?

Former Member
0 Kudos

Hi Experts,

I made a mistake that,

Actually, I want to DELETE a TRansport, so, first, i wanna to delete the child , so, I highlighted the child but, by mistake I pressed the red truck button....its RELEASED!!!!

So, Wht I hv to do now? my intention is I hv to delete the entire transport?

Can I leave as is? into the trsnaportaion layer?

or once I released, I hv to IMPORT to test system?

is still, I hv chnace to DELETE the transport?

response apprecialted.

thanq

Edited by: SAP ABAPer on Sep 3, 2008 11:59 PM

1 ACCEPTED SOLUTION

Former Member
0 Kudos

I would suggest creating a new TR reverting the changes(which you can do by retirieving the previous version) and then move both the changes to QA.

If you leave it as it is and if some other developer touches the same object he will take your unwanted changes with his transport.

2 REPLIES 2

Former Member
0 Kudos

I would suggest creating a new TR reverting the changes(which you can do by retirieving the previous version) and then move both the changes to QA.

If you leave it as it is and if some other developer touches the same object he will take your unwanted changes with his transport.

suresh_datti
Active Contributor
0 Kudos

There is NO need to migrate the (unwanted) Released Transport Request. You can have it deleted from the Buffer by your BASIS team.