actual overhead costs calculation

Hi,

i've got a probleme with actual overhead costs calculation in PS.

I plan costs on activity elements for activity types. i've got costing sheets and costing variants for actual and planned values.

when i do ctrl+f10, the planned values are calculated for the activity type and its associated overhead costs. (no need to launch t-code cj46)

then i do enter times in cat2, transfer them to ps through cat5, the hours are valudated in the activty element but not the overhead.

i always have to use cj44 to transfer actual overhead to project.

is this t-code a compulsory step to transfer overhead costs to PS? or is my costing variant not properly customized?

regards

xavier

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Sep 03, 2008 at 01:10 PM

    you have to run period end process to allocate actual overhead costs (CJ44)

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      You sound like an expert in project systems. Can you please advise how to make the overhead allocations (t.code CJ45) transaction currency to adopt the object currency instead of the controlling area currency. Currently the transaction currency is adopting from the controlling area currency.

  • Sep 03, 2008 at 01:55 PM

    Hi Xavier,

    i have couple of questions regarding overhead and material costs postings to projects.

    1.Where did you assigned cost sheet?to WBS or Network?please help me.

    2.Where do you post your materials costs?to network or WBS?

    3.where do you settle production order on project? to WBS or to Network?

    any help is appreciated.

    Thanks,

    Anusha

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Xavier,

      i have couple of questions regarding overhead and material costs postings to projects.

      1.Where did you assigned cost sheet?to WBS or Network?please help me.

      at the lowest level, activity element in my case

      2.Where do you post your materials costs?to network or WBS?

      at various levels, wbs, network and activity element

      3.where do you settle production order on project? to WBS or to Network?

      i've never done that so i can't help

      any help is appreciated.

      Thanks,

      Anusha

  • avatar image
    Former Member
    Jul 16, 2009 at 12:53 PM

    Hi,

    Please confirm have you assigned costing sheet in the valuation variant used in actual cost costing variant ?

    T-code OPL1.

    I think defaulting costing here should calculate overhead as it does at planning phase.

    Thanks

    Saikishore.Ganga