Skip to Content
avatar image
Former Member

Data Exchange CRM <--> ECC Sales transactions

Hi SAP CRM experts,

We have a requirement where the sales orders created in sap crm should be changed in R/3 and then the changes should come across to crm and again the order should be editable in crm.

I did some research on this and came across the following;

1. There are 3 different scenarios X, Y and Z which can be activated using middleware in order to make R/3 as the source system. But in this case the changes of R/3 are not transferred back to CRM and the order becomes undeditable in CRM.

2. Interdependent Changes: In this case the orders are editable both in CRM and R/3 but with lot of restrictions and mainly that the changes in R/3 will not be reflected in CRM.

Can you please help if there is some standard solution to make CRM orders editable in both CRM and R/3 and the changes flow to both systems and orders are in sync.

Thanks a lot.

Satish Soni

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 05, 2008 at 06:20 AM

    Hi Satish,

    Refer Note : 888665 - Scenario A - Customizing Settings

    Regards,

    Shalini Chauhan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 03, 2008 at 09:44 AM

    Have a look at szenario A, this is what you want to set up - it is standard since 5.0. Do not worry about the limitations, usually they do apply only in about 5% of the projects. Also in this scenario all R/3 changes are reflected in CRM as far as the data fields are available there.

    Regards, Kai

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Sorry, but I did not have access to the system so the note number was from my recordings. I got the error corrected now, it is 642944, but you might also check note 889051 - "Scenario A: Overview and settings" which refers to alot of other notes.

      Hope this helps,

      Kai

  • avatar image
    Former Member
    Sep 10, 2008 at 07:09 AM

    Hi Satish,

    To change the order before replicatingt o R/3 we can do this through BADI CRM_DATAEXCAHNGE_BADI .

    I did the same thing which you want ..i have implenetde badi to modify address no which is creating accodig to BP...i have restriced it with some functionality in above BADi...so if you want to do some chanes to order before replacation to R/3 you can do in this BAdi

    You have to just create the Z implemenattion for above BADI defination and map the required fileds in particular method.

    Regards,

    Amol Tambe

    SAP CRM technical Consultant.

    Add comment