With what value finish product as come when we do goods recipt from prd

Hi,

With what value finish product as come when we do goods recipt for oa prodution order in make to order scenerio.

The material is not talking standard price form th e material master when we are doing goods recipt.

Regards,

somiraghu

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    Sep 03, 2008 at 07:17 AM

    Hi,

    Generally, Sales Order Stocks are valuated separately not as per the Standard Price or MAP of the Material Master. So, it will take value of the components issued and Operation Cost (from Activity types)

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 03, 2008 at 08:16 AM

    If you use non-valuated sales order stock (account assignment E) there will ne no value posting at all during GR, thus also no accounting document. The full actual costs (that Pankaj listed) will be posted during settlement of the production order.

    Regards,

    Kay

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 07, 2009 at 05:35 AM

    As per costing varient.The value of material is updated.