Hi All,

Can PS be used for Opex project? Normally i use it for capex project using Investment management.

Please advice.

If it can be used ...how can we put the opex budget ?

Cheers,

nies

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 03, 2008 at 08:48 AM

    No constraints from system if you wish to use PS for Opex Projects.

    If it's a real project (refer definition of project) you can capture the Operational Expense using WBS's (projects) otherwise you use cost centre or internal orders as cost objects.

    Budgeting would be possible if you use WBS or IO but not cost centre.

    Regards

    Sreenivas

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 03, 2008 at 09:30 PM

    Hi Nies,

    If your customer is a manufacturing/process industry you can use the Investment management to hold OPEX budget and distribute to WBS which contains service orders, maintenance orders attached.

    If your customer is public sector then you can use budgeting functionality from Funds Managment (BCS).

    Regards

    Srinivasan Desingh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 07, 2008 at 09:52 PM

    You can also try using budget categories in investment management to capture both capex and opex for the same WBS