on 09-02-2008 12:46 PM
We are having Internal Orders from 1999 till date ( approx 3000 nos) in 'Techniaclly Completed' status.Now I need those to be converted into 'closed' status.
Tell me the process.
.
Hello
Technically technically complete and close is same meaning. Order with technically complete cannot be used for posting
however you can put closed indicator through KO02
Regards
Dinabandhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In addition to above if you have any due of settlements use TCode
KO88 - Individual Processing and
KO8G - Collective Processing
Cheers
Srinivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Snivas,
If you want to proceed with the Status change of all of the IOs together, there is the KOK4 transaction where you can select the Function "Complete" and the system will close (system status) the Internal Orders that don't have any related document opened (like a PO opened, for example).
Otherwise, if you want to run the Status change for a single IO, you can use KO02 transaction.
Normally we only close the Internal Orders after the Month-end processing when they are not useful for the users.
I hope it helps you.
Regards,
Daniel.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.