Budget report help S ALR 87013558

Hi ,

I am little bit Confused about the budget report

T CODE: S ALR 87013558

That is BUDGET/ACTUAL / COMMITMENT/REMORDPLAN/ASSIGNED.

What I understand is

Assigned = ACTUAL + REMORDPLAN + COMMITMENT

Commitment ( OPEN PR and OP AND AFTER GR its reduce)

Can any explain

Actual and rem ord plan

Please give example .

thanks

sunil

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 02, 2008 at 10:39 AM

    Hi Sunil,

    Assign value = (actualcommitmentrem.order plan)

    actual values comes after GRN(goods receipt note) for material. or after service entry for service.

    if we are using network costing also in our project then cost frem this comes under remain order plan.

    suppose you create a purchase order of 1000 rs value then in 558 report there will show 1000 rs in committment column.

    suppose you create GRN of 500rs for same PO then 500 rs will come in actual and other 500 will show in commitment.

    (I think it will help to you. For any furthur query reply me.)

    Regards

    lallan