Budget report help S ALR 87013558

former_member214272
Contributor
0 Kudos

Hi ,

I am little bit Confused about the budget report

T CODE: S ALR 87013558

That is BUDGET/ACTUAL / COMMITMENT/REMORDPLAN/ASSIGNED.

What I understand is

Assigned = ACTUAL + REMORDPLAN + COMMITMENT

Commitment ( OPEN PR and OP AND AFTER GR its reduce)

Can any explain

Actual and rem ord plan

Please give example .

thanks

sunil

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sunil,

Assign value = (actualcommitmentrem.order plan)

actual values comes after GRN(goods receipt note) for material. or after service entry for service.

if we are using network costing also in our project then cost frem this comes under remain order plan.

suppose you create a purchase order of 1000 rs value then in 558 report there will show 1000 rs in committment column.

suppose you create GRN of 500rs for same PO then 500 rs will come in actual and other 500 will show in commitment.

(I think it will help to you. For any furthur query reply me.)

Regards

lallan

former_member214272
Contributor
0 Kudos

Hi lallan ,

Thanks now Actul value is ok now ,

but still I am not clear the meaning of REM.ORDER PLAN

Thanks

sunil

Former Member
0 Kudos

Hi Sunil,

Suppose you are using network cost planning for a projects.

when you assign any activity to the WBS and then material component to that activity to ctrae any Prq. so in this case the moving price or stnd. price of that material master multiplies with qty that you entered for PR. the result of this calculation comes under remain order plan.

I think now you understand. for furthur query reply me.

regards

Lallan......

former_member214272
Contributor
0 Kudos

Hi lallan

thanks for your fast response

problem slove.