Hi All,
Could you please help me in how to monitor the progress completion of a project using only WBS . For example :
Project Building ( WBS level 1)
Wbs activity 1 (WBS level 1)
Wbs activity 2 (wbs level 2)
Wbs activity 3 (wbs level 3)
I would like to monitor let say the progress of WBS activity 1 and wbs activity 2.
what should i do?
Cheers,
Nies
Hi,
Assign "milestones" in those WBS's with "progress analysis" indicator ticked.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Friends,
I am also interested in carrying out Progress Analysis using WBS.
Most of my study has revealed that it is not feasible to carry out PA using WBSE. If its possible to get BCWS, BCWP, EV etc using WBSE only it would be very helpful in my scenarion.
Regards,
Seemant
Edited by: Seemant Parth on Sep 4, 2008 10:46 AM