on 09-02-2008 9:02 AM
Hi,
I have a problem with displaying activities planned in calendar. My date profile has date type orderactual and orderpropos.
but in calendar activities are shown in a day = orderactual (so the day when activity was scheduled, not a day when activity is to be done (orderpropos)).
how can I deal with it?
can calendar be configured?
regards
Radek
in calendar activities with date orderactual are displayed, and if it is not filled then with date orderplanned.
i just had to make orderactual clear, and fill orderplanned for planning.
when activity is closed orderactual is filled.
regards